WIN LOCK 2B INDUSTRIAL DEVELOPMENT PROJECT: POURING 1,200M³ OF SUPERFLAT FLOOR CONCRETE BEFORE THE NEW YEAR
January 24, 2025

In the bustling atmosphere of the year's final days, the Win Lock 2B Industrial Development Project is busier than ever. On January 21 and 23, 2025, the construction team successfully completed the superflat floor concrete pouring for two zones, covering a total floor area of 4,400m² with a concrete volume of 1,200m³.

Each batch of concrete was poured on schedule in a flurry of activity. The Construction Committee and workers collaborated seamlessly, ensuring strict control over safety, concrete quality, and the perfect flatness of the floor surface, meeting the highest standards of a modern industrial project.