With a spirit of responsibility, proactivity, and professionalism, Viteccons' construction force demonstrated smooth and effective coordination in pouring concrete for the typical floor slab. From meticulous preparation, optimized batching plant operation, to strict quality control and surface finishing after pouring, every stage was carried out rigorously to ensure progress and absolute adherence to technical requirements.
Regarding this phase of implementation, the concrete pouring took place continuously from 3 AM to 11 AM on the same day, completing an impressive total concrete volume of 240m³. This clearly demonstrates the capability and professionalism of the Viteccons team in accelerating project progress.